This page shows 1 programs where this organization is recorded as implementer. Counts only; no money. Not recorded: prime or sub, money before FY2017, headquarters, local or international.
The headline numbers. Counts only; each opens the list behind it. Source: query layer
3 documents name this organization.
| Document | Role | Year | Type | Country |
|---|---|---|---|---|
| Infrastructure needs program II : middle area desalination plant expansion, Gaza blending tanks, and network improvements environmental assessment report PA-00S-XPW | author | 2016 | Assessment | Gaza Strip |
| Roads Economic Study PA-00S-XQ2 | author | 2014 | Reference Document | West Bank |
| Assessment study for failures on various USAID-funded roadways PA-00M-2V8 | author | 2012 | Assessment | West Bank |
Sector areas by decade, as a grid, a map and a Gantt. Placement uses the program, not the organization. Source: program sector profile
| Sector | 2010s | Programs |
|---|---|---|
| Economic Growth | 1 | |
| Health | 1 |
Not placed in one country: 0 regional and 0 global programs, 0 with no location classified. Places that documents only mention are not shown as places it worked.
A picture of all lineage links among this organization's programs, grouped by country or sector. Source: succession links, program scope
Black and Veatch Special Projects Corp. ran 1 program in 1 country. The biggest clusters are West Bank/Gaza (1).
Counts exclude 1 support mechanisms and untyped keys. Years are start years by award or document (basis shown in the table below).
? Likely, not confirmed No lineage links are known for these programs yet. That does not mean none exist: links are found from document text, and only some are recorded so far.
Show lineage links is off: there are no links to show.
Rows are countries; regional and global programs have their own rows and are never a country. Dot placement is the program's start year; a program whose own years begin long before this organization's evidence is placed at the organization's first evidence year.
One row per program this organization is recorded as implementing, with years, role and what came after. Source: implementer records
1 program, earliest start first unless sorted by documents. Role on every row: implementer (prime or sub is not recorded).
| Program | Country or scope | Years | Sector | Documents |
|---|---|---|---|---|
Infrastructure needs program II (INP II)Details
| West Bank/Gaza | 2012 to 2017 | Economic Growth, Health | 31 |
Who inherited the work: the same firm, another firm or government. Source: succession links
Kept by the same firm 0; passed to another firm 1 (0 stated, 1 likely, not confirmed); handed to government or a local organization 0; successor implementer not recorded 0; no successor on record 0 of 1 programs.
| Before | After | Link | After is run by | Evidence |
|---|---|---|---|---|
| Unnamed program (award AID-294-TO-13-000114, implementer APCO/ArCon Construction and Services, LLC, 2014) 2014 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| Unnamed program (award 294-TO-16-00001, implementer APCO/ArCon Construction and Services, LLC, 2016-2017) 2016 to 2017 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| Deir Sharaf main pipeline project 2014 to 2015 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| West Bank and Gaza infrastructures needs program (INP) II 2014 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| multiple roads project north area (MRNII) 2014 to 2015 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| Unnamed program (award 294-TO-13-00015, implementer APCO/ArCon Construction and Services, LLC, 2014-2015) 2014 to 2015 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| Infrastructure needs program II (INP II) 2012 to 2017 | Unnamed program (award 294-TO-16-00001, implementer APCO/ArCon Construction and Services, LLC, 2016-2017) 2016 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | another firm: APCO/ArCon Construction and Services, LLC | 0 sources |
| Multiple Roads Project South-(MRSII) West Bank and Gaza 2014 to 2015 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
| Unnamed program (award 294-TO-13-00016, implementer APCO/ArCon Construction and Services, LLC, 2014-2015) 2014 to 2015 | Infrastructure needs program II (INP II) 2012 to 2017 | ? Likely, not confirmed succeeded; likely, not confirmed | before this organization's program | 0 sources |
Organizations that co-implemented programs with this one. Prime and sub are not recorded. Source: shared programs
Black and Veatch Special Projects Corp. worked with 2 partner organizations. The most frequent is Black and Veatch International (1 program), then The Morganti Group, Inc. (1 program).
Black and Veatch Special Projects Corp. is at the center; the ring shows at most 10 partners, ordered by shared programs clockwise from the top. Line width and circle size are shared programs. Host governments are not listed. Partners the registry has not typed are unknown.